AC Hotel National Landing

Arlington (Crystal City), VA

Emily Alyssa Photography

01 / 14

Emily Alyssa Photography

02 / 14

Emily Alyssa Photography

03 / 14

Emily Alyssa Photography

04 / 14

Emily Alyssa Photography

05 / 14

Emily Alyssa Photography

06 / 14

Emily Alyssa Photography

07 / 14

Emily Alyssa Photography

08 / 14

Emily Alyssa Photography

09 / 14

Emily Alyssa Photography

10 / 14

Emily Alyssa Photography

11 / 14

Emily Alyssa Photography

12 / 14

Emily Alyssa Photography

13 / 14

Emily Alyssa Photography

14 / 14

Project Highlights

  • Renovated 355 guestrooms, including seven newly created rooms.

  • Full public space transformation with lobby expansion and new prep kitchen.

  • Exterior upgrades featuring a refreshed façade, hardscape, and patio.

  • Conversion of an abandoned swimming pool into a modern fitness center.

  • Creative phasing and sequencing allowed the hotel to remain operational throughout construction.

  • Achieved GMP eight months post-acquisition and began construction nine months post-acquisition.

AC Hotel National Landing

Overview

Project Scope

The former Marriott Crystal City at Reagan National Airport in Arlington, VA underwent a dynamic 28-week conversion to become the AC Hotel National Landing, completing its transformation in Spring 2025. This $21.3 million renovation encompassed nearly 200,000 square feet of upgrades, including a striking new building façade, exterior hardscape and patio enhancements, and a full public space reinvention. The lobby was expanded to create a modern, open-concept arrival experience, while the abandoned swimming pool was converted into a state-of-the-art fitness center. Additional scope included a new prep kitchen, renovations to existing guestrooms, and the creation of seven new keys—bringing the total to 355 guestrooms.

AC Hotel National Landing