Project Highlights
The preconstruction and model room work allowed for the development of accurate plans, schedule, and discovery of unforeseen conditions.
Development of VE options were a direct result of work completed during preconstruction and the model room phase.
Successfully managed two (2) separate ownership schedules concurrently; one for the guest rooms portion and the other for the owner condominiums.
Renovation included installation of a new owner-designed FF&E package.
Areas of the property remained occupied during the renovation, allowing maximum revenue generated with minimal disruption to daily operations.
![W Fort Lauderdale](https://www.firstfinish.net/wp-content/uploads/2019/04/MGM4201-HDR-e1554812502939.jpg)
Overview
Project Scope
The project was completed in 26 weeks after eight (8) weeks of pre-construction and covered 323,100 square feet of space. The renovation included 266 guest rooms, 121 owner condominiums, and corridors.
![W Fort Lauderdale](https://www.firstfinish.net/wp-content/uploads/2019/04/MGM4201-HDR-e1554812502939.jpg)