Project Highlights
More than 75% of renovated guest rooms received tub-to-shower conversions with linear drains, glass shower doors, and new glass barn doors.
Guest rooms received full finishes upgrades to include VWC, paint, LVT flooring, tile, barn doors, and a full FF&E package.
Upgraded life safety system, and installed new thermostats and lighting throughout the property to increase energy efficiency.
![The Westin O’Hare](https://www.firstfinish.net/wp-content/uploads/2020/10/v2.2-0674-scaled-e1602530891439.jpg)
Overview
Project Scope
The project was completed in 37 weeks and covered 237,000 square feet of space. The renovation consisted of 525 guest rooms including 390 tub-to-shower conversions, and 10 corridors.
![The Westin O’Hare](https://www.firstfinish.net/wp-content/uploads/2020/10/v2.2-0674-scaled-e1602530891439.jpg)